CANINO - ITALY

CANINO - ITALY

Project Date
10/07/2019 - 31/05/2020

Type of plant
EPC  PV Revamping

Client
Phenix Renewable srl

 

Group 50Peak Power

24,4 MWp

 

In 2019 ESI worked as EPC for the revamping of a photovoltaic power plant of 24,4 MWp in the area of Viterbo, in the so - called district Sugarella.

The plant, already existing and in function for 7 years, registered serious problems both on the functioning and the sustainability.
ESI has carried out the revamping of the PV modules, tracker and the low voltage distribution line.